The order a Malta fit-out has to happen in
A shell form fit-out is ten trades in a fixed order. This is that order, why it cannot be shuffled, and the specific points where a swap costs you money.

A shell form fit-out is not a list of jobs. It is a sequence, and the sequence is the part that decides whether a project runs to programme or spends three weeks waiting for somebody who could have been booked earlier.
The ten trades in the budget calculator are listed in the order they happen. That is not a presentation choice — it is the build order, and the calculator adds them up in the same sequence a site actually runs.
The order
- Insulation
- First fix electrics
- First fix plumbing
- Gypsum and plastering
- Screed
- External doors and windows
- Internal doors
- Floor and wall tiling
- Second fix electrics
- Painting
Some of these overlap in practice. On a larger property the plasterer can be working on one floor while first fix is still running on another. What cannot happen is a trade arriving before the one it depends on, and there are four dependencies that are not negotiable.
The four points where the order is not a preference
First fix before plaster
Electrics and plumbing go in while the walls are open. Once the plasterer has been, every cable and every pipe is behind a finished surface. Moving a socket after that means cutting the wall, re-plastering the patch, and repainting the wall — three trades returning to undo one decision.
This is why the socket and lighting layout has to be settled before first fix, which is much earlier than most people expect. You are deciding where a table lamp goes before you have chosen the table.
Screed before tiling
The screed is the level, flat base the tiles are laid on, and it has to cure. Tiling onto a screed that is not ready is the failure that shows up a year later as cracked grout and loose tiles, and by then the only fix is to lift the floor.
Apertures before internal finishing
Windows and external doors close the building. Until they are in, the property is open to weather and dust, and no finishing trade should be working in it. This is also the item most likely to hold up everything else, because apertures are made to measure and their manufacturing time is not part of the trade sequence at all — it runs in parallel and has to be started early enough to land here.
On our own rate card, external doors and windows are the largest single line in a fit-out. They are also the one most capable of stopping a programme.
Second fix after painting
Sockets, switches and light fittings go on last, after the walls are painted. Fitting them first means either masking every one of them or painting around them, and both look like what they are.
What the sequence means for decisions, not just trades
The practical consequence is that the decisions arrive in a different order from the one people expect. The things you choose first are the things you cannot see:
- Where every socket, switch and light will be — before first fix
- Whether any ceiling is being dropped, and where — before plastering
- The aperture specification — early enough for manufacture
- Bathroom layout and waste positions — before first fix plumbing
The things you choose last are the visible ones: paint colours, light fittings, ironmongery, furniture. Those can move late without costing anything.
That inversion is the single most useful thing to understand about a fit-out. Most people arrive with the finishes decided and the services vague, and the sequence needs it the other way round.
Where a managed programme actually earns its money
Any competent trade can do its own part. What goes wrong on an unmanaged project is the joins: the plasterer arriving before first fix is signed off, the tiler waiting on a screed nobody scheduled, the joiner unable to measure because the walls are not finished.
Running the whole sequence under one contract means those dependencies are somebody's job rather than nobody's. That is most of what a prime contractor does, and it is why the same ten trades cost differently depending on who is holding the order.
What this article does not tell you
It does not tell you how long any of it takes. Our rate card establishes the order, not the calendar — durations depend on the size of the property, how many people are on site, and what the survey finds once work starts. A programme with real dates comes after a survey, not from a web page.
Common questions
- Can trades not just work at the same time?
- Some can, and on a large property they do — plastering one floor while first fix runs on another. What cannot happen is a trade working before the one it depends on. The dependencies are fixed even when the calendar is flexible.
- How long does each stage take?
- We do not publish durations, because they depend on the size of the property, how many people are on site and what the survey finds. The sequence below is fixed; the calendar against it comes from the programme after a survey.
- What is the single most expensive ordering mistake?
- Deciding socket and lighting positions after first fix. Everything else on this list can usually be worked around at some cost. That one means opening walls that have already been plastered, and it is the most common regret we hear.
What we could not establish
- Durations. Our own rate card establishes the order the trades happen in, not how long any of them takes — that is a function of property size, crew size and what the survey finds.
- Lead times for ordered items. Apertures and joinery are made to measure and their manufacturing time sits outside the trade sequence entirely.
Sources
- Turnkey.mt budget calculator rate card (js/main.js) — Turnkey.mt · read 2026-09-01
Drafted with Claude — claude-opus-5, then read, corrected and approved by Neil Bennett before publication. We do not publish anything a person has not read.